TICKET NUMBER #1786 | UPS Vacuum Oil 4 x MMU
Date & Time
Date: 10th & 11th January 2023
Start Time: 8:00 AM
End Time: 4:00 PM
Activities
10th Januray
9:30 AM: Switching load from utility to engine generators.
Perform UPS101 – MMUs maintenance by Piller.
3:30 PM: Switching load from engine generators to utility.
4:00 PM: All equipment back to normal status (utility supply).
11th January
8:20 AM: Switching load from utility to engine generators.
Perform UPS102 – MMUs maintenance by Piller.
2:30 PM: Switching load from engine generators to utility.
4:00 PM: All equipment back to normal status (utility supply).
Authorised Personnel
Our Electrician will also be on-site for the duration.
The maintenance activities are scripted to a technical reviewed Maintenance Operation Procedure (MOP).
DCA’s in-house maintenance engineer shall provide the overall technical backup, support, and supervision.
DCA’s Facility Manager shall coordinate all site activities.
Expected Outcome
We do not anticipate any issues.
We apologize for any inconvenience you may experience during this activity. Your cooperation and understanding will be greatly appreciated.